PMP Practice Questions #51

You are managing a 12-month complex project characterized by many uncertainties. While the deliverables are defined, stakeholders suggest focusing on delivering and validating the scope at the project’s end.

As a project manager, what is the BEST approach to ensure the right value delivery in this scenario?

A) Formulate the project scope by incorporating all assumptions and uncertainties, focusing on project delivery at the end.
B) Identify risks associated with uncertainties in value delivery and escalate them to the project sponsor for guidance.
C) Plan Conducting frequent evaluations of the project’s value and periodic scope validation reviews throughout the project duration.
D) Suggest dividing the project into distinct phases, with each phase culminating in a milestone review to assess progress and value.

Analysis

This question addresses a complex, 12-month project marked by substantial uncertainties yet with well-defined deliverables. Here, stakeholders prefer to validate the project scope only at its conclusion. The query underscores the importance of consistent evaluations and scope validations. These are key strategies for effectively managing uncertainties and ensuring the successful delivery of value. The focus of the question is to determine the best approach for achieving these objectives in such a challenging project environment.

Analysis of Options:

Option A: Formulate the project scope by incorporating all assumptions and uncertainties, focusing on project delivery at the end. This approach might not sufficiently address the evolving nature of changes and risks throughout the project’s lifecycle, potentially overlooking critical adjustments needed during the project’s progression.

Option B: Identify risks associated with uncertainties in value delivery and escalate them to the project sponsor for guidance. This involves identifying risks and escalating them to the project sponsor for guidance. The initial part of identifying risks is appropriate, but solely escalating these issues without further management or tracking is insufficient. It lacks proactive management and risk mitigation. Escalation should be reserved for situations where the issues are beyond the project manager’s control.

Option C: Plan Conducting frequent evaluations of the project’s value and periodic scope validation reviews throughout the project duration. This approach is effective in managing uncertainties as it allows for timely identification and resolution of issues, ensuring the project remains aligned with its objectives. Regular evaluations facilitate prompt adjustments to the scope, schedule, or resources, enhancing the project’s adaptability and maintaining its value delivery in dynamic environments.

Option D: Suggest dividing the project into distinct phases, with each phase culminating in a milestone review to assess progress and value. Suggests dividing the project into distinct phases, with milestone reviews at each phase’s end to assess progress and value. This phased approach is good for structure and periodic assessment. However, compared to Option C, it might be less effective in a highly uncertain environment, as waiting for phase completion for validation may not be frequent enough.

Conclusion: Option C is the most suitable approach. It addresses the need for frequent and periodic evaluations, essential in a project with high uncertainties. This approach ensures continual alignment with project goals and adapts to changes, thereby maximizing the potential for successful value delivery. It offers a balance between structured project management and flexibility required in uncertain scenarios. Additionally, it aligns with key project management tasks like executing projects with urgency and managing scope effectively.

PMP Exam Content Outline Mapping

DomainTask
ProcessTask 1: Execute project with the urgency required to deliver business value
ProcessTask 8: Plan and manage scope

Topics Covered

  • Validate Scope
  • Early and Incremental Feedback
  • Leadership
Was this article helpful?
3.8 out of 5 stars

2 ratings

5 Stars 50%
4 Stars 0%
3 Stars 0%
2 Stars 50%
1 Stars 0%
Please Share Your Feedback
How Can We Improve This Article?